Temperature-91 Deg and size is 12". Whether I should increase the CWC in only spool or in the whole pipeline so that whole expansion and Vitrual Anchor Length is decreased?.
Thank you for the reply.
Temperature-91 Deg and size is 12". Whether I should increase the CWC in only spool or in the whole pipeline so that whole expansion and Vitrual Anchor Length is decreased?.
Dear RAJATH
To better answer your question we need to know pipeline scheme. Could you provide us with it?
Is 755 mm too much? Maybe it is a mistake?
Considering your question about incresing thickness of concrete shell - I may assume that it could not give you expected result.
Regards,
J.V.