Thread: Tie-in Spool Connection between Riser and Pipeline

  1. #1

    Tie-in Spool Connection between Riser and Pipeline

    Hi,

    I am facing a problem in Tie-in spool design which connects Pre-installed Riser and Pipeline. The Expansion in the pipeline is 755mm and Virtual Anchor length is 1788m. The concerete thickness of pipeline is 50mm. the maximum displacement allowed near riser bend is 200mm, even after providing 2 90 degree bend(Expansion Spool) i am not able to limit the displacement to 200mm as the displacement is coming as 500mm. I am following the design of DNV 1981. Can anybody tell me how to minimize the displacement?

    Regards,

    Rajath

  2. # ADS
    Spons Circuit
    Join Date
    Always
    Posts
    Many
     
  3. Re: Tie-in Spool Connection between Riser and Pipeline

    Whats your design temperature? Pipeline size? The simplest i can think of a quickie is to increase the CWC thickness

  4.    Sponsored Links



    -

  5. #3

    Re: Tie-in Spool Connection between Riser and Pipeline

    Thank you for the reply.

    Temperature-91 Deg and size is 12". Whether I should increase the CWC in only spool or in the whole pipeline so that whole expansion and Vitrual Anchor Length is decreased?.

  6. Re: Tie-in Spool Connection between Riser and Pipeline

    Dear RAJATH
    To better answer your question we need to know pipeline scheme. Could you provide us with it?
    Is 755 mm too much? Maybe it is a mistake?

    Considering your question about incresing thickness of concrete shell - I may assume that it could not give you expected result.

    Regards,
    J.V.

Similar Threads

  1. Subsea Pipeline And Riser
    By gepachir in forum Pipeline And Fluid Flow
    Replies: 11
    Last Post: 08-28-2016, 07:12 AM
  2. Pipeline and Riser
    By mamz in forum Pipeline And Fluid Flow
    Replies: 0
    Last Post: 07-14-2013, 10:38 PM
  3. Replies: 1
    Last Post: 07-30-2012, 11:29 AM
  4. Tubing connection interchangeable with PH6 connection
    By dunglan in forum Drilling And Workover
    Replies: 2
    Last Post: 04-26-2011, 08:58 AM
  5. Replies: 0
    Last Post: 02-27-2011, 12:14 PM

Tags for this Thread

Bookmarks

Posting Permissions

  • You may not post new threads
  • You may not post replies
  • You may not post attachments
  • You may not edit your posts
  •  
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40