full list:
EN 1536:2010+A1:2015 Execution of special geotechnical work - Bored piles
EN 1537:2013 Execution of special geotechnical works - Ground anchors
EN 1538:2010+A1:2015 Execution of special geotechnical work - Diaphragm walls
EN 12063:1999 Execution of special geotechnical work - Sheet-pile walls
EN 12699:2015 Execution of special geotechnical works - Displacement piles
EN 12715:2000 Execution of special geotechnical work - Grouting
EN 12716:2001 Execution of special geotechnical works - Jet grouting
EN 14199:2015 Execution of special geotechnical works - Micropiles
EN 14475:2006 Execution of special geotechnical works - Reinforced fill
EN 14475:2006/AC:2006 Execution of special geotechnical works - Reinforced fill
EN 14490:2010 Execution of special geotechnical works - Soil nailing
EN 14679:2005 Execution of special geotechnical works - Deep mixing
EN 14679:2005/AC:2006 Execution of special geotechnical works - Deep mixing
EN 14731:2005 Execution of special geotechnical works - Ground treatment by deep vibration
EN 15237:2007 Execution of special geotechnical works - Vertical drainage
missing A1 from 2015 for this two standards:
EN 1536:2010+A1:2015 Execution of special geotechnical work - Bored piles
EN 1538:2010+A1:2015 Execution of special geotechnical work - Diaphragm walls