In a pipeline design project that does not span more than 2km, is it necessary to have an alignment drawing? I think a GA drawing should suffice.
In a pipeline design project that does not span more than 2km, is it necessary to have an alignment drawing? I think a GA drawing should suffice.
Can any specialist in the house respond to this?
Alignment Sheets are more helpful and explainable for pipelines because these illustrates pipeline elevations and locations on different but continuous intervals (normally at 25m or 30m span).