  1. Exclamation House Load Test in Power Plant

    Dear All!
    Now I have trouble with my project's Performance test.
    Do you know any Standard (ASME, EU, BS, DIN...) that require this test for new power plant (Coaled fire, PC type).
    Could you give one project had successful this test (For reference only).
    Thanks a lot

  2. # ADS
    Spons Circuit
    Join Date
    Always
    Posts
    Many
     
  3. Re: House Load Test in Power Plant

    This is often required in areas with less stable power grids. The plant typically requires special design features to operate continuous and stable at such a low load (usually <10%) but can and has been done many times.

  4.    Sponsored Links



    -

  5. Re: House Load Test in Power Plant

    Thank you very much for your information.
    That mean it is not in Standards and was contract clause only between Owner vs Contractor.
    Do you know any jobs that be successful test with fuel of anthracite coal.
    Hope your answer asap.

  6. #4

    Re: House Load Test in Power Plant

    Normaly this kind of test is called ISLAND TEST because is the operation of the power plant isolated of the Grid and supply only the auxiliary power + eventualy any consumer power (steam or and electricity). You put the unit connect to the grid at FULL LOAD and after you open the grid breaker.

    This is a very complicated test for the power plant:

    - If is coal, we only can run the power plant may be 30m - 60 m and after you need to trip or increase the load;
    - If is a CC then it is possible to run in auto mode and stay in this mode the time that you want bacause the GT control can run very easly to lower loads and you trip the ST runing in BYPASS.

    In any case the power plant MUST have the BYPASS SYSTEM (HP and LP pressure, minimum HP).

    The power plant control change of LOAD CONTROL to FREQUENCY CONTROL. The test is very hard if the load change = NOMINAL POWER- AUXILIARY POWER is bigger and for coal is much dificult because you need to prepair the coal mils (before put mils operate in half load, because you need to trip imidiatly after the open of the breaker and operate with only one, ...but the minimum power of a coal boiler is 30%-40% nominal, so you need the BYPASS to put the extra steam that you canot put on the ST.
    In CC this is much more easly.

Similar Threads

  1. All you need to know about Power Plant Engineering
    By matthewbig in forum Engineering Certificates
    Replies: 9
    Last Post: 01-15-2018, 09:25 PM
  2. Crude oil Treatment plant for Gas Turbine Power Plant
    By ganvel in forum Oil And Gas Process
    Replies: 0
    Last Post: 02-28-2014, 07:56 PM
  3. Power plant drive test procedure and tuning
    By daoviettuan in forum Electrical & Power Engineering
    Replies: 0
    Last Post: 07-05-2013, 04:32 AM
  4. load list power
    By farchan in forum Electrical & Power Engineering
    Replies: 0
    Last Post: 07-02-2013, 04:28 AM
  5. Replies: 7
    Last Post: 08-12-2011, 09:44 AM

Tags for this Thread

Bookmarks

Posting Permissions

  • You may not post new threads
  • You may not post replies
  • You may not post attachments
  • You may not edit your posts
  •  
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40