<

Results 1 to 7 of 7

Thread: Difference between Front End Engineering Design (FEED) and fabrication/construction?

  1. #1

    Difference between Front End Engineering Design (FEED) and fabrication/construction?

    Can anyone explain the difference between Front End Engineering Design (FEED) and fabrication/construction in oil and gas sector? And also, what do Front End Engineering actually do? Thanks.

  2. # ADS
    Spons Circuit
    Join Date
    Always
    Posts
    Many
     
  3. #2
    The FEED takes place upstream the detailed engineering studies. It covers all the process engineering studies for a given project. Typical documents produced during the FEED are:
    - PFD & Block diagram
    - P&ID and line list
    - Utilities & general facilities distribution and line list
    - Equipment data sheet
    - Control valves datasheet
    - Cause an effect chart

    I hope that this clear enough.

  4.    Sponsored Links



    -

  5. Feed ?

    FEED: Front End Engineering & Design

    This the first stage of Engineering for any Project (Chemical / Petrochemical / Oil & Gas / Refinery etc) where the following discussed & decided.

    1. Technical / Process Wise:
    a. Material Balance (Mass & Heat)
    b. Process Flow - How the various raw materials flow from start to end & in what form
    c. Major equipments of the process - pumps, vessels, heat exchangers, filters, etc
    d. Safety Systems requirement for process

    Engineering Wise:

    1. Approximate Load List - for motors, transformers, drives, High Voltage Switchgear, UPS size, Diesel Genertor requirements etc
    2. Utilities required for the process - Air compressors, Nitrogen Plant, Fire Fighting systems, Hot Oil Heating Systems requirement, Air Dryers etc
    3. Major Instrumentation Systems - PLC / SCADA / DCS system (which one or combination of the above etc)
    4. Approximate Instrument List - Kind of Networks used, kind of Instruments used, system architecture (rough sketch / drawing showing the different networks connectivity between them)


    Management Wise:

    a. The total cost of the project - around X +20% approximation (within the accuracy of +/- 20% accuracy)
    b. The total manpower requirement for the plant
    c. Total List of Raw Materials requirement & their quantities
    d. Approximate time required for completion of the project

    Philosophies wise:

    1. Plant Operating Philosophies / Plant Design Philosophy & design Basis
    2. Instrumentation Engineering philosophy - Design & selection basis documentation
    3. Control Systems Philosophies - Heirarchies being implemented, design basis for selection of PLC / SCADA / DCS Systems, Third Party Interfaces, OPC Interfaces, Serial Interfaces between systems, Interfaces between DCS, ESD, F&G systems
    4. Safety Shutdown Systems philosophy - LOPA Studies / HAZOP studies / CHAZOP studies etc including SIL calculations.

    Now apart from the above, the following are the deliverables at the end of the FEED.

    1. Mass & Heat Balance Calculations
    2. Process Flow Diagrams
    3. Process & Instrumentation Diagrams (only 70 - 75% accurate)
    4. Load list for electrical
    5. Major Equipments & their Sizing (Major Equipments 100% accurate, however, there might be an addition of a one or two pumps / motors / blowers that might get added during the detail engineering stages but not vessels / heat exchangers or tanks).
    6. Instrument list - which is 80% to 90% accurate.

    However, please do remember the following:

    1. Instrumentation Datasheets / Process Datasheets / Mechanical Datasheets are not the deliverables of FEED. They are preapred during the Detail Engineering Phase
    2. Instruments Selection, Sizing Calculations are finalized / done during the detail engineering phase only.


    Hope i am correct. However, request senior professionals to comment on the same.

    Sastry Musti
    Instrumentation & Control Systems Engineer

  6. thank you for the usefull info

  7. I like how Sastry has broken the answer into different philosophies. I will try to answer in a more basic way
    FEED - Done by Engineering Contractor (FEL-1 is business planning focused, FEL-2 - PFD focused, FEL-3 is P&ID focused). FEL-2/3 also involves significant work by all engineering disciplines (Mech, Inst, piping, electrical, CSA etc)

    Fabrication - usually done by a vendor or fabrication company who is contracted by the engineering (FEED) contractor. Fabrication of vessels, columns, reactors based on specifications provided by the engineering contractor or maybe a technology licensor.

    Construction: is done by a construction contractor. Can be same as engineering contractor (in cases like Bechtel etc) or a purely contruction company. The construction company works on the design of the engineering company to install / erect equipment made by fabricators.

  8.    Spons.


  9. Daffodils,

    Thanks for the reply & for a very short & sweet yet complete information regarding the FEL / FEED. Well done sir.

    Sastry

  10. Re: Difference between Front End Engineering Design (FEED) and fabrication/constructi

    Dear Sastry & Daffodils

    Very informative. May I detail information for Mechanical Engineering discipline in FEL 2/3 please?

    Many Regards,
    Deven

Similar Threads

  1. FEED (Front End Engineering Design)
    By dhnsekaran in forum Oil And Gas Process
    Replies: 37
    Last Post: 03-28-2025, 06:04 PM
  2. Replies: 20
    Last Post: 09-07-2015, 11:04 AM
  3. FEED & DEtail Engineering
    By ramesht906 in forum Petrochemical
    Replies: 2
    Last Post: 03-26-2014, 02:56 PM
  4. Replies: 0
    Last Post: 07-03-2011, 11:13 PM
  5. Front End Engineering
    By nomanfahmi in forum Petroleum Refining
    Replies: 0
    Last Post: 09-12-2009, 06:49 PM

Tags for this Thread

Bookmarks

Posting Permissions

  • You may not post new threads
  • You may not post replies
  • You may not post attachments
  • You may not edit your posts
  •  
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40