Hello,
I'm working inoil & gas project. I have problem with grounding calculation study ( STEP & Touch voltage) witch fault current to be considered .
for information the substation is composed by :
-Transformer 11/6.6 kV with NER limit current to 300 A &
- Transformer 6.6/0.72 kV direct earthed
EPC Contractor taken the limited current of 300 A as fault current. Is it correct?
What's the best practice.