Ratawy reservoir checking :
Descending production tubing of 2 7/8 inches till the bridge ending and checking the top of the bridge plug at 3503 m with 2 tons.
Removing the completion mud by fresh water, checking the bridge with a pressure of 1500 psia.
Hanging the production tubing at 3473 m and putting the charismas’ tree .
Making the perforation (3482-3488 m) with ceramic shots ,1 11/16 inches -density 13shots/m .The tubing head pressure raised immediately to 600 psia, opening the well to flowing 100l/min.
Continuing the well production and clean-up (very viscous oil).
Acidizing the perforations mentioned above with acid( HCL 12% HF 3%)(circulating pressure 3600 psia and injection rate 400l/min).
Opening well for clean-up. Measuring well rates with different choke sizes.
Closing well for build-up. killing the well with a 1.25 gm/cc brine and a ½ inch choke and controlling the well.
Putting and checking the 9 inches BOP.
Pulling the production tubing, and setting a bridge plug (BP)at 3453m to isolate perforations.
Descending again the production tubing to check the BP, after that the tubing was pulled till 2600m and a cement plug was set and verified at 2513m.
Removing the brine by sodium chromite .
Controlling the well, hanging the production tubing at 2300m , putting charisma's tree and checked with a 6500 psia.
Moving the rig to another location.
----------------------------------------------------------------------