Thread: Pipe Analysis Calculation Problem - Pipe Schedule

  1. Pipe Analysis Calculation Problem - Pipe Schedule

    Anyone out there give me a hand here? This is the first task my company has asked me to do for them.

    "Please could you determine pipe schedule for the following arrangement:

    4940 level (4940 ft) pipe entry point into No 4 shaft, flow 120 l/s. Assume Sch. 40 pipe.
    5900 level (5900 ft) intermediate level with BAC using 60 l/s
    6500 level (6500 ft) intermediate level
    7500 level (7500 ft) intermediate level
    8500 level (8500ft) bottom level using 60 l/s

    Please could you use the ASME B31.3 piping code to specify the pipe schedule changeovers and recommend a pipe support strategy. Assume Victaulic pipe couplings type 77 are used. For 80 Sch and above piping type 808 couplings (double grooved type ) will be used.

    Please assume the pump peak pressure bottoms out at 600 kPa. Please do the calculation with and without a water hammer allowance in the design pressure variable."


    Any help would be great!

    Thanks

  2. # ADS
    Spons Circuit
    Join Date
    Always
    Posts
    Many
     
  3. Re: Pipe Analysis Calculation Problem - Pipe Schedule

    It seems you are trying to estimate the pipe wall thickness using only hydraulic data... if so, you won't need the ASME B31.3 at all...

    On the other hand, if you want to estimate the minimum pipe wall thickness you will need Design Pressure and Temperature figures... and, by the way, it also seems you are dealing with a pipeline... If so, you have to use ASME B31.4 (for Liquid Pipelines) or ASME B31.8 (for Gas Pipelines).

    As your supervisor for orientation...

    Cheers

  4.    Sponsored Links



    -

Similar Threads

  1. Riser Stress Analysis-Pipe-in-Pipe
    By quynhchau84 in forum Pipeline And Fluid Flow
    Replies: 0
    Last Post: 07-17-2013, 04:36 AM
  2. Replies: 2
    Last Post: 06-20-2013, 11:13 AM
  3. [ask] pipe calculation
    By dan in forum Pipeline And Fluid Flow
    Replies: 3
    Last Post: 09-08-2010, 12:01 AM
  4. Pipe grade & pipe Schedule
    By WAT in forum Pipeline And Fluid Flow
    Replies: 14
    Last Post: 05-11-2009, 06:02 AM

Tags for this Thread

Bookmarks

Posting Permissions

  • You may not post new threads
  • You may not post replies
  • You may not post attachments
  • You may not edit your posts
  •  
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40