    Hi everybody here!
    I have problem for SIL verification of an exiting f&g (fire & gas) detection system,
    the problem is evaluating the amount of PFD (probability of failure on demand).
    In my opinion PFD evaluation for f&g system is different from common SIF in process system,
    because in the case of exiting a disturbance in process all redundant sensors sense the disturbance and the probability of failure for all of them is equal. because they are a system of for example 2oo3 and we evaluate SIF's PFD for them.
    But in analogous f&g system by 2oo3 voting system, there is no equal probability of sensation of gas concentration by three sensors. one or two or three sensor detect the gas cloud and when we evaluate PFD we are not sure that they sense the cloud really or no!???? so we dont know there is any demand or no?! and if we have not any demand the calculation of PFD will be meaningless.
    therefore How we can evaluate the amount of SIL?
    This article was originally published in forum thread: SIL study of F&G system started by hamidkeng View original post
    Comments 1 Comment
    1. josefreitas's Avatar
      josefreitas -
      In probabilistic mathematics if you have 3 sensors in paralell you can calculate the probability of two of three detect at same time - its a conditionated probability.
  • .

  • Recent Threads

    Eddie

    asme b 18.31.2

    Thread Starter: Eddie

    Please, Could you share the following ASME standard (in their latest edition)?:
    - asme b 18.31.2

    Last Post By: Eddie 05-27-2026, 09:03 AM Go to last post
    nicers

    Dlt cad 2025

    Thread Starter: nicers

    Available DLT CAD 2025 for exchange
    I need Powerfactory Digsilent 2026

    Last Post By: nicers 05-26-2026, 02:28 PM Go to last post
  • .

  • ..

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34 35 36 37 38 39 40