For your problem 1....I suggest that if there is no well control problem (loss/gain)......you may continue drilling as there is very short interval remaining.
2. Bit was drilling with 5 ft/hr which has dropped to 2.7 ft/hr which shows that bit has got dull........with an avge rop of 2.7 ft/hr. you have to spend 18 more hours to reach TD........You have already used your bit for 15 extra hours.....so you must not take risk and POOH to change bit instead of using the same bit for 18 more hours (if ROP does not drop further).....
3. Answer to this question requires a lot of information.......e.g.
a) on bottom and off bottom torque before this problem occured.....
b) on bottom /off bottom pressure before and after the problem.....
c) either you are expecting any formation change at the depth you are drilling.
there may be many possible reasons for ROP drop.......such as
1. your bit has become dull due to an extremely hard formation encountered
2. as your hole angle is 55 degree.......means almost wors case of hole cleaning.....may be due to poor hole cleaning you can not drill further (on/off bottom torqe is almost same indicating this possibility)
3. your string may be twisted off.......pressure can give you some indication about this.