Pipe Analysis Calculation Problem - Pipe Schedule
by
Published on 01-29-2013 02:38 PM
Anyone out there give me a hand here? This is the first task my company has asked me to do for them. "Please could you determine pipe schedule for the following arrangement: 4940 level (4940 ft) pipe entry point into No 4 shaft, flow 120 l/s. Assume Sch. 40 pipe. 5900 level (5900 ft) intermediate level with BAC using 60 l/s 6500 level (6500 ft) intermediate level 7500 level (7500 ft) intermediate level 8500 level (8500ft) bottom level using 60 l/s Please could you use the ASME B31.3 piping code to specify the pipe schedule changeovers and recommend a pipe support strategy. Assume Victaulic pipe couplings type 77 are used. For 80 Sch and above piping type 808 couplings (double grooved type ) will be used. Please assume the pump peak pressure bottoms out at 600 kPa. Please do the calculation with and without a water hammer allowance in the design pressure variable." Any help would be great! Thanks