Sorry man* Deleted.
Sorry man* Deleted.
.................................
Hi all*
would anybody please share unlocked PF version 15.2.X* 2016* or 2017?
Tnx
hi bookie1 and others. I was tried to contact with some of others here that have the solution (I think) for this version and 2016 or 2017 without success. I don´t understand what is the purpose to write here that they have the solution and then they get quiet. I thought in this place they share their work with us but they didn´t it. Nobody answer to our requests. Nobody answer our PM. I don´t understand.
My hardware ID is: F89ADC-BCA3E8
Can u please help me?
Thankyou very much in advance.
Hallo ionioni*
Please help me My hardware ID is: F89ADC-BCA3E8
I need the user and the Key. Thankyou very much in advance.
Hallo ionioni*PF Digsilent 2016
Please help me My hardware ID is: CMa//1HnCajvejHlIgbASA==
I need the user and the Key. Thankyou very much in advance.
Hello sir,
I'm Doing thesis work in optimal storage planning in IEEE 34 node Radial test system. I'm using DigSilent Powerfactory for load flow calculations. In that i had doubts. Please clarify me sir.
1) How the Substation to be defined, in that software only busbar type substation defined and is there any source to be incorporated?
2)Is General load element to be defined for any voltage level?
Please reply as much as possible
Read the Tutorial document. It show substation.
The substation is the busbar itself, you can rename it.
Yes, the general load voltage is depend on the busbar voltage connected to.
--------------deleted----------
dopost
Hello Sir,
Thanks for your reply.I face an issue While Execute the IEEE 34 node Radial Test feeder system, after 14th Iteration there exist an error "No convergence in Load Flow". How to rectify that error?