Qa/Qc Documents
Construction Quality Plan
WPS/PQR/WQT Records
Tank Erection Procedure
Welding Consumables Control Procedure
Hydrostatic Test Procedure for Completed Tank
Pneumatic Test Procedure for Roof Welds
Pneumatic Test Procedure for Reinforcement Pads
Procedure for Calibration of Welding Equipments
Procedure for Calibration of Electrode Oven
Hardness Test Procedure
PWHT Procedure
Vacuum Box Test Procedure
Settlement Measurement Procedure
ITP (Mechanical Works)
Liquid Penetrant Test Procedure
Radiographic Test Procedure
Material Summary Report and Material Map
Material Test Certificate
Weld Map
Weld Inspection Summary
Weld map and NDT Summary
Thanks
Thanks
Thanks
Can someone post these documents from any of the gulf oil n gas companies except aramco
Qa/Qc Documents
Construction Quality Plan
WPS/PQR/WQT Records
Tank Erection Procedure
Welding Consumables Control Procedure
Hydrostatic Test Procedure for Completed Tank
Pneumatic Test Procedure for Roof Welds
Pneumatic Test Procedure for Reinforcement Pads
Procedure for Calibration of Welding Equipments
Procedure for Calibration of Electrode Oven
Hardness Test Procedure
PWHT Procedure
Vacuum Box Test Procedure
Settlement Measurement Procedure
ITP (Mechanical Works)
Liquid Penetrant Test Procedure
Radiographic Test Procedure
Material Summary Report and Material Map
Material Test Certificate
Weld Map
Weld Inspection Summary
Weld map and NDT Summary