Hi all,
I have a case here wish to share and seek for answer.
Current project involved in subsea equipment, fluids came out from well is 65 degree c. Current used coating is jotamastic 87 3 coat epoxy system unable with with stand this temperature due to insulation requirements. Is this true? Any test done before over 65 degree c?


Sigma coating used but adhesion test needs to wait for 7 days. This 7 days is that state in all coating standards or I need to refer sigma spec said curing time 5 days? I need to get the coated item into production line, how fast and what method/standard I can used to avoid this 7 days adhesion test? Please advice.