    read this thread:

    [link Point to another website Only the registered members can access]

    For quick calculation:

    let's say we have 3 wells, the latest testing rate of each like A1(200bpd), A2(100bpd), A3(300bpd) => the sum of all the test rates is (200+100+300=600bpd), however,the actual rate we got from the 3 wells was (550bpd).

    Allocation Factor, AF= (Total actual rate / Total test rate) = 550/600

    the allocated rate for each well is:
    A1=(550/600)*200=183bpd
    A2=(550/600)*100=92bpd
    A3=(550/600)*300=275bpd

    Last edited by petengr; 05-19-2013 at 10:27 AM.

  2.    Sponsored Links



    -

  •   

Similar Threads

  1. SIL allocation tools
    By livorno in forum Safety And Environment
    Replies: 0
    Last Post: 07-13-2014, 12:17 PM
  2. Production Allocation Method
    By aanzola in forum Oil And Gas Production
    Replies: 6
    Last Post: 09-05-2010, 04:05 AM
  3. back-to-back test for speed increased gear box
    By giova70 in forum Mechanical Engineering
    Replies: 1
    Last Post: 03-22-2010, 07:14 PM

Tags for this Thread

Bookmarks

Posting Permissions

  • You may not post new threads
  • You may not post replies
  • You may not post attachments
  • You may not edit your posts
  •